Home Forums Discussion MS Project 2016 – Updating Master projects containing sub=projects

This topic contains 5 replies, has 3 voices, and was last updated by  Jakob Ooms 2 weeks, 1 day ago.

Viewing 6 posts - 1 through 6 (of 6 total)
  • Author
    Posts
  • #409835 Reply

    Hello,

    We have a master project that contains several sub-project. When the projects were loaded, they were loaded as “Read-Only” so that the Program Manager could simply see the updates.

    However, when you open the Master Project, the sub-project updates are not there. How do we get the Master Project to pull the updated information from the sub-projects?
    Thanks.

    #409838 Reply
    Larry Christofaro
    Larry Christofaro
    Participant
    • Community Leader
    • Expert
    • Forum Pro

    Norman, can you elaborate your statement about loading projects “read-Only”? Does that mean that they are unlinked when they are loaded into the master? If that’s the case then absolutely, they will not be updated. Otherwise I could use some additional details. Thanks…

    #409844 Reply

    Hi Larry
    I go to Project/Sub-Project then find my project and select the mode “Read-Only” and leave the “Lin to Project” checked.
    This prevents the Program Manager from checking out all the sub-projects while they review the overall schedule.

    However, as mentioned, the project update are not coming in.

    Thanks…

    #409851 Reply
    Larry Christofaro
    Larry Christofaro
    Participant
    • Community Leader
    • Expert
    • Forum Pro

    Interesting Norman. I’ve never used that read only feature before, but I did a quick test (created a master with one sub – read only, saved the master, opened / changed / and closed the sub, opened the master again…and the changes came through). So I’m kind of lost with what you have you test. Can you try a simple test similar to what I just did and see if you get the same results?

    #409907 Reply

    Thank you Larry for the feedback.
    It appears that if the sub-project is “minimized” that it does not update. If you expand the sub-project, it looks for it and updates it just fine. This is what I have told the Program Manger to do.

    Thank you again for your feedback.

    #410455 Reply

    Jakob Ooms
    Member

    Hi Norman,
    I have the same issue, with the subprojects not updating % work complete, remaining work etc until opening the subproject in the master project. Do you know if this is the only way to ‘refresh’ the %completes or if project has a mechanism to do it automatically?
    Thanks!

Viewing 6 posts - 1 through 6 (of 6 total)
Reply To: MS Project 2016 – Updating Master projects containing sub=projects
Your information:




68 − = 64