MS Project Calendar IF Condition (Advanced)

Home Forums Microsoft Project Discussion Forum MS Project Calendar IF Condition (Advanced)

  • This topic is empty.
Viewing 2 reply threads
  • Author
    Posts
    • #481598
      ah.bedewi
      Participant

      I want to know how could I enter the if statement mentioned to the standard calendar in project. “If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday, then Monday will be given as a day off.”

      Does anybody can provide a auto solution to it.

    • #481610
      Daryl Deffler
      Guest

      Not the solution you’re looking for, but create a Project calendar based on the standard calendar. Manually scan it for any conditions, such as a holiday on a weekend, and manually mark the appropriate Friday/Monday as a non-working day. Not sure of the need for the “If” logic, but once you’ve marked the day(s) as non-working, all Project functions such as scheduling will work appropriately.

    • #481614
      Jerome
      Guest

      To the best of my knowledge, formulas only work on custom fields, they cannot be used to change default fields. Your best option is to follow Daryl’s advice.