Hi,
I have this error message prompt at the Resource Center when selected more than 100 resources from my department for Capacity Planning. Seems like there’s a limitation here in Project Online. Are there any setting provided to configure the number of resources selected for capacity planning? Would like to allow more resources to be selected for capacity planning.
Hi Chee. The message is pretty specific about > 100 resources and I don’t know of a practical option to override. Another option to allow for more resources is a Power BI report. There are multiple Power BI content packs that can provide this feature immediately with some nice visuals. Hope that helps…