  • #415751 Reply

    Chaz

    I get these incorrect variances in line 1 below. I’ve added a new “Test” task and it calculates correctly.

    Baseline Start Start Start Variance Baseline Finish Finish Finish Variance
    Line 1 GO-LIVE Release 1 11/8/19 11/19/19 30 days 11/10/19 11/21/19 30 days
    Line 2 Test Go-Live Task 11/8/19 11/21/19 7 days 11/10/19 11/21/19 7 days

    Has anyone seen something like this?