I get these incorrect variances in line 1 below. I’ve added a new “Test” task and it calculates correctly.
Baseline Start Start Start Variance Baseline Finish Finish Finish Variance Line 1 GO-LIVE Release 1 11/8/19 11/19/19 30 days 11/10/19 11/21/19 30 days Line 2 Test Go-Live Task 11/8/19 11/21/19 7 days 11/10/19 11/21/19 7 days
Has anyone seen something like this?