Home Forums Discussion MSP not baselining when I append to template from Excel

This topic contains 3 replies, has 2 voices, and was last updated by Larry Christofaro Larry Christofaro 7 months, 1 week ago.

Viewing 4 posts - 1 through 4 (of 4 total)
  • Author
    Posts
  • #409448 Reply

    Rose

    I have a template which includes calendars and resources, when I import my project from excel using append to current project, and then set a baseline, Project does not set the baseline, there are no error messages, but when I add the column Baseline Start it just contains NA.

    The resource initials in my excel project are the same as the ones in the template.

    Project does seem to baseline if I highlight some tasks and then baseline on selected tasks; however this doesn’t work for all tasks and my schedule is very long so to do this for the whole schedule would be tedious.

    Project will also let me copy and paste the start date into the Baseline Start column.

    Does anyone know what could be going wrong or what I could do to overcome this problem?

    #409449 Reply
    Larry Christofaro
    Larry Christofaro
    Participant
    • Community Leader
    • Expert
    • Forum Pro

    Rose… My first gut feel is that it is a bug somewhere in Project, but it would be interesting to figure out what the cause might be. If you don’t get an answer from someone else I’d be glad to see what I can do by looking at the schedule itself, if that’s OK with you. Reply with a request and we can work through it offline.

    #409761 Reply

    Rose

    Hi Larry, we managed to figure out the problem. It was linked to the resources and calendars that were already loaded into MSP file. One of the resources had the wrong calendar allocated to it, and for activities when the dates and times were not within the calendar times MSP would not baseline them. By allocating the correct calendar to the resource we were able to fix the problem. Thanks

    #409762 Reply
    Larry Christofaro
    Larry Christofaro
    Participant
    • Community Leader
    • Expert
    • Forum Pro

    Thank you Rose for replying to this message with what you found out. Glad to hear that all is well with Microsoft Project.

Viewing 4 posts - 1 through 4 (of 4 total)
Reply To: MSP not baselining when I append to template from Excel
Your information:




2 + 8 =