I’m sure I must be missing something very simple here.
I have a project that was baselined, then for various reasons a revised programme was agreed with the client and I created a Baseline 1.
I want to be able to view a progress line against this new baseline 1, however, I can’t find anywhere to change which baseline is used to create the progress line.
Adam, I didn’t see any option to set which baseline to use for the progress bar. I suggest, which I teach as best practice, to always use Baseline as your current baseline. Then use Baseline1-10 for historical baselines. All variance fields and views use Baseline and it is easier to use those as is then creating all your own calculations. You can use the Set Interim Plan to copy baselines (IE: copy Baseline to Baseline2, then Baseline1 to Baseline, then Baseline2 to Baseline1). Then use Clear Baseline to clear Baseline2. hope that helps…
That’s unfortunate, but somehow doesn’t surprise me. Too many classes just teach the mechanics. It’s understandable as they are trying to cram a lot in to a session, but still unfortunate.