I’m looking for a guidance on assigning resources. I have project where all budgeted resources – material, cost, and work – have been estimated at the top job/project level.
Material Resource #1
Material Resource #2
Material Resource #3
Work Resource #1
Work Resource #2
Work Resource #3
Task #1
WP #1
WP #2
WP #3
The project will have many Tasks each with the same WP’s. It is repetitive work so the only thing changing is the location of the Task. How do I assign my resources to each WP? If Material Resource #1 is $250,000 (for the entire project), how do I assign a portion of that to a WP? The same would apply for the work and cost resources.
Additionally, how do I track the actual cost of each resource. At the start of the project there will be a lot of cost spent on material resources. I don’t want one of the WP to have to absorb the cost of this large cost. Create an acquisition task?