      I Have a question regarding single point adjustments. We use MSP 2016 and Cobra. When setting S=P=A, you can have a +/- adjustment. You can have a negative adjustment in Cobra for a given month, but MSP does not allow, and you do not want to change the history as to how the hours/dollars were spread. How is this then typically addressed in EVM programs using MSP? Looking to ensure cost schedule integration. Do you just set S=P for MSP, and S=P=A in Cobra?