Show Holidays on Gantt Chart Project 2010

Home Forums Microsoft Project Discussion Forum Show Holidays on Gantt Chart Project 2010

Viewing 5 reply threads
  • Author
    Posts
    • #160937
      Alasdair
      Guest

      Wondering if anyone has had a requirement to show holidays on the Gantt Chart in Project 2010? Is it possible to show holidays with the resource name alongside and show the task also with their name alongside. Creating a separate task for holidays is a work around, but though there should be a better way? Can anyone help?

    • #165066
      Sabina
      Guest

      I too have this question. If I am using Enterprise calendars for each person to show their holidays, how can I then see whole teams of people and when they are on holiday? I don’t want to set up a dummy project for holidays as that would still allow people to book resources that are on holiday in other projects.

    • #196037
      Lavinia Lung
      Guest

      I found this add in, which can produce you a new report based on resources calendar. You can see the screenshots.
      Let me know if this helped you!

    • #196123

      Lavinia,

      You can use this one for free:
      Representing Non-Working Time as Tasks in Microsoft Project by Jan De Messemaeker (MVP)
      https://users.online.be/prom-ade/project_en.htm

      Regards,
      Ismet

    • #196230

      Lavinia, I presume you are Marketing Project Manager for Power2Plan. So I guess you are the right address to ask for “Why don’t you offer free trial ?”. Regards, Ismet

    • #206219
      Lavinia Lung
      Guest

      Hi Ismet, that’s right. I’m the Marketing Project Manager. We do have a trial, sorry that I didn’t reply to you earlier. I’ll be happy to try it and give an opinion about it. 🙂 Regards, Lavinia