Home Forums Discussion subproject dependencie to master project

This topic contains 3 replies, has 2 voices, and was last updated by Jigs Gaton Jigs Gaton 5 days ago.

Viewing 4 posts - 1 through 4 (of 4 total)
  • Author
    Posts
  • #412299 Reply

    Hi

    Is it possible link the inserted subprojects to master project?
    Explain: I have inserted a subproject (summary task with 5 subtasks) on a master project.
    I pretend that this subproject have the same duration of master project althought the variances will be.
    If i increase the duration of the master project then the subprojecct automatically will also increase.

    #412303 Reply
    Jigs Gaton
    Jigs Gaton
    Member
    • Author

    Subproject are linked to master projects by default, no? The master shows the duration of accumulated project durations + the master project duration.

    #412307 Reply

    Hi Jigs

    I did not explain my issue correctly:

    I have a master project with 100 activities/tasks with a milestone task of conclusion.

    Later i insert a small subproject (5 tasks)

    I would like to have dependencies between the last task of my master project and my subproject summary task.

    Then if i track the tasks of master project will have automatically impact on the subproject inserted.

    Other way How can i constraint (start and finish) the subproject with the master project?

    Regards,

    Carlos Santos

    #412310 Reply
    Jigs Gaton
    Jigs Gaton
    Member
    • Author

    Have you tried not linking the Subproject summary task, but the first task in the subproject group?

Viewing 4 posts - 1 through 4 (of 4 total)
Reply To: subproject dependencie to master project
Your information:




14 − 5 =