Home › Forums › Microsoft Project Discussion Forum › Task Indicator shows delay but there is no dates in the column
Tagged: indicator
I created a project template that will be uploaded to the project server. In it is a Column field for Task Indicator that are Red (delay), Green (Active/On Track) and Yellow (Risk of delay). In the first few lines, the indicator is showing RED but there are no dates. Any assistance will be appreciated. Thanks.
Charan, will need more information than just that. Is it working correctly for lines beyond the first few? Are these manually scheduled tasks, are the other tasks auto-scheduled? What is different with these first few tasks than with the other tasks? Let us know and will help if I can. Thanks…
Hi Larry, Thanks for responding. I did a little more testing and removed all the dates, it shows RED (Delay) in all the columns. This should be Auto-scheduled.