Unable to change Summary Task constraint type to ASAP.

Home Forums Discussion Forum Unable to change Summary Task constraint type to ASAP.

Viewing 1 reply thread
  • Author
    Posts
    • #523798
      JEOstbye
      Participant

      Hi!
      I have an IMS I’ve inherited that was ALAP. I want to change it all to ASAP so we can calculate float, etc. I can change any and all sub tasks to ASAP but I cannot for the life of me figure out how to update the summary tasks to ASAP. I get options of FNLT, ALAP, SNET. That’s it. Help? :/

    • #523994
      Jason
      Guest

      Click Project Tab
      Click Project Information button
      Click Schedule from Dropdown
      Select “Project Start Date”

Viewing 1 reply thread
  • You must be logged in to reply to this topic.