Home › Forums › Discussion Forum › Unable to change Summary Task constraint type to ASAP.
Tagged: ALAP, As Late As Possible, summary tasks
Hi!
I have an IMS I’ve inherited that was ALAP. I want to change it all to ASAP so we can calculate float, etc. I can change any and all sub tasks to ASAP but I cannot for the life of me figure out how to update the summary tasks to ASAP. I get options of FNLT, ALAP, SNET. That’s it. Help? :/
Click Project Tab
Click Project Information button
Click Schedule from Dropdown
Select “Project Start Date”