Variation in the duration of a task depending on predecessors and / or successor

Home Forums Discussion Forum Variation in the duration of a task depending on predecessors and / or successor

Tagged: 

Viewing 1 reply thread
  • Author
    Posts
    • #478979
      guy forget
      Participant

      Is there a way to make the duration of a task automatically adjust based on predecessors and / or successors. Ex: Three finish to start tasks A, B, and C. I want the duration of the task ” B ” to adjust automatically if the end of the task ”A” and / or the start of the task ” C ” change in time,

    • #479183
      Daryl Deffler
      Participant

      Guy;
      MS Project supports something called “Hammock Tasks” where the duration of one task is dependent on other tasks. I found this MPUG article which may help.
      Not sure if this is exactly what you’re looking for.

      https://www.mpug.com/dos-and-donts-using-hammock-tasks/

      Hope this helps