I’m using a main project with 5 sub-projects. One of the sub-projects is a resource pool. When I try to level two tasks from different sub-projects the ‘Level Selection’ menu is disabled? Why would that be the case?
Thanks,
Dan
Dan,
Its been a while, But I believe you need to select more than one task, then select the Level Selection option. Meaning you need to make the selection before you try to click level selection.
Hope that helps
Daryl,
I wish it were that simple. I’m trying to level two tasks from different sub-projects and it’s not enabling.
Any other ideas?
Thanks,
Dan
Do either of the tasks have actual start dates? Can you post an image to show?
Ben,
Nope. They’ve both got an Actual Start date = N/A. I’ve posted a screen grab here. Let me know if you can’t read it.
Thanks,
Dan
Any hints Ben?