Building a schedule on an "ordinal calendar"

Home Forums Discussion Forum Building a schedule on an "ordinal calendar"

Viewing 1 reply thread
  • Author
    Posts
    • #106589
      Ron Lefebvre
      Guest

      I have built a level 1 schedule in Project with an assumed start (award of contract) date. The client now wishes the schedule to be shown in “ordinal months”, meaning (I assume this from the context of the request) that the start date is 0 mnths, and the completion of various tasks and milestones is to be shown as so many months after the start or award of the contract. (the project is approx. 20 months long).

      Is there a way for Project to calculate these dates (formatted in months from start) so that I do not have to calculate them manually (about 150 tasks)?

      Thanks, Ron

    • #106677
      Sai Prasad
      Participant

      Yes, you can. I hope this is what you expect https://i.imgur.com/IncQTUz.png

      Step 1: Insert a custom field Duration1 to your View. This column will have a formula that subtracts the task finish from the project start date
      Step 2: Right the column. Select Custom Fields. Select Formula and enter the formula ProjDateDiff([Project Start],[Finish]).
      https://i.imgur.com/wECRYzH.png
      Step 3: Default units of Duration is days. Select File backstage, Options, Schedule. Change the “Duration is entered in” to months.