Is it possible to have updates to a Project using Sharepoint without actually uploading the project to SharePoint. I need to be able to receive inputs from 100+ foremen about 1000+ jobs without all of them being able to actually touch the project.
Yes, you can sync a list of tasks with SharePoint. Your team members can view the schedule and update their work in SharePoint, and you’ll see the changes in Project. And vice-versa. Do expect, as per the documentation, if there are more than 100+ tasks the sync will be slower. Know more on how to use this feature at https://support.microsoft.com/en-us/office/sync-with-a-sharepoint-tasks-list-fb956d2c-723d-4d5a-b7e5-710ef82aa27a and https://docs.microsoft.com/en-us/office/troubleshoot/project/sync-with-tasks-from-project
Let’s know if this helps
We are running up against the 2,000 site limit. We have to keep our project sites for audit for ten years. Microsoft has no answer for what to do. Does anyone have a solution? We were thinking about copying the site to another domain, but the Microsoft tools don’t recognize the Project Online SharePoint as a site.
thanks!