Home › Forums › Microsoft Project Discussion Forum › Project 2010 View of Predecessors and Successors
Tagged: quickbooks error 15227
Hi All,
I am new to the MPUG Forum but hope I can get the assistance I need. I ‘m using Project 2010 Pro (desk top) and need to see my driving predecessors and driven successors when examing a task. I am not refering to task inspect which does not provide the views on the predecessors / successors columns. I saw asomeone else using these tools to analyze their schedule but I didn’t get an opportunity to asked them to explain how to me. I appreciate all input.
Thanks, Paul
That feature (i.e., Task Path) is only available in Project 2013. See the related article here: http://office.microsoft.com/en-001/project-help/highlight-how-tasks-link-to-other-tasks-HA102891930.aspx
You can download a trial and start using Task Path feature.
Regards,
Ismet Kocaman | ikocaman.pm@gmail.com
Paul:
Not sure if references to specific companies are allowed on this thread, but Aztech International (at goaztech.com) has a free utility (Run!23) which is a demo of their extended offerings, and it contains a tool/button: TRACE, which will generate either all Successors pushed or all Predecessors pushing any task. I use it every day.
Joe
Joe, They do not respond to registration for the free tool. — Ismet
Hi Paul,
While in Gantt chart view, you can choose Details and then show the Task form at the bottom. In the task form you can choose(right click) to show predecessors and successors. As you scroll through the tasks in the Gantt chart, the corresponding predecessor and successor tasks shows up in the Task form.
Not sure if this is what you want, but it helps to review the schedule for me.
In Project 2010 the Task Inspector shows only the driving predecessor.
Microsoft Office Project Server is a project management server solution made by Microsoft. It uses Microsoft SharePoint as its foundation, and supports interface from either Microsoft Project as a client application or by web browser connecting to its Project Web App (PWA) component.
70-647 Study Material
70-662 Test Questions
Thank you exactly what I was looking to see the successor detail for mapping
Hi Team,
in the bottom view, showing details,can we also get to see the dates of the predecessors and successors as well?
Paul
Paul,
You can see the task information (including dates) for the predecessors and successors when you double click on them in the predecessors & successors detail view. I prefer to use the trace macro, which sets flag 5 to yes for predecessors/successors. Then sort by start or finish and you can see the flow of activities with dates/durations, etc. Hope that helps!
Tim
There’s a set of free macros – called QuickTrace – at one of my blog entries. That tool sets and applies a filter for predecessors or successors of any selected task, including “driving” or not. It works pretty well, though you have to be comfortable with macros to install and customize it.
Paul’s request is kind of standard for anyone needing to efficiently evaluate logical relationships in a schedule. It’s available as a minor feature of the logic analyzer add-in that I use. I wrote about it in another entry.
Let’s read through all of the symptoms of this error. An on-screen pop-up error message is the main symptom of Quickbooks error 15227. When the error occurs in the system, the active program crashes. The system often crashes when an error occurs. Windows works slowly or does not respond to the keyboard and mouse inputs error makes the security app invisible or missing. The taskbar is also not recognized if the error is found.
Paul – I agree with James on using Task Form. If you need something graphical, you can use Relationship diagram. Once you split the view, change the Details from Task Form to Relationship diagram (using More views). The relationship diagram will display the selected task in the middle with its immediate predecessor(s) and successor(s) to its left and right as boxes.