Do not understand.
I ll explain better my issue
Have a Project with almost 1.000 tasks.
All tasks have work resources assigned.
Now we decide to set s new calendar to the project.
The Project summary task changed the duration, all tasks were not affected.
Than i realized that the calendar of all resources did not change to the Project new calendar, In the resource sheet.
Have I to change the calendar in each resource? Or there is s quick way to do that?
Carlos, In Resource Sheet view, change the base calendar of all the work resources to the new (base) calendar. This change will inherit the workweeks and exception of the bar calendar to the resource calendar.
Thank you for your answer.
You are saying to change all work resources calendar as:
First filter resources type to work on resource sheet
2nd in the calendar column change the calendar to the new one for all work resources.
Is that it?