I have a trace macro that I can share if anyone’s interested. It will trace predecessors, successors, or both. It sets Flag 5 to yes. The code was from a PDF file that came with an MS Project 2003 book. I only had to make a few small changes to get it to run. Let me know and I can post the code for the macro.
Larry, Thanks – much appreciated! It’s been happening for a while with a few different MS Project files, but that’s a great suggestion to take a closer look at the printer and print driver.
Tim
Paul,
You can see the task information (including dates) for the predecessors and successors when you double click on them in the predecessors & successors detail view. I prefer to use the trace macro, which sets flag 5 to yes for predecessors/successors. Then sort by start or finish and you can see the flow of activities with dates/durations, etc. Hope that helps!
Tim
Thanks James – looks like a difference between 2013 and 2010 (I’m using 2010 stand alone).
Tony – Sorry I didn’t see this when you posted – hope you have it working now.
Daryl,
Thank you very much! It’s a huge help to understand exactly how Project displays the increments. This will save us a lot of time trying to figure this out – we’ll look at changing the reporting periods if that’s possible. Your time and expertise are much appreciated.
Tim
Brian,
Here’s the link to my blog post from 2013 on how to create a 30-day look ahead custom view in MS Project 2010. The 30 days can be adjusted for longer or shorter timeframe.
Daryl – Thanks for sharing the article on custom reports. That’s a nice way to do it as well.
Hope this helps!
Tim
Not sure if this helps with your question Jayakumar, but I wrote this formula to return the “% Should Be Complete” to flag activities that have not been updated to the status date. The formula shows the % that should be complete as of the status date. Then I compare that to the (actual) % Complete field to identify activities that need status update.
IIf([Scheduled Finish]<[Status Date],”100″,IIf([Scheduled Start]<[Status Date] And [Scheduled Finish]>=[Status Date],Round((ProjdateDiff([Scheduled Start],[Status Date])/[Scheduled Duration])*100,0),0))
This helps me in a large schedule to quickly see activities that are not at their expected % complete value.