Back to ArticlesBack

Join 50,000+ PM Professionals

Get expert PM insights, PMP prep tips, and earn PDUs with exclusive content delivered weekly.

Protected by reCAPTCHA: Privacy & Terms

MPUG - Master Project User GroupMPUG - Master Project User Group

Wayne from Santa Fe, NM asks: I created a project containing 400 tasks. After entering the tasks I realized that my calendar wasn’t correct and made some changes. I also changed the Calendar options. The changes affected the task durations as well as the assignments and didn’t result in what I was hoping for. What did I do wrong?

Ellen answers: You have discovered a feature that all levels of Microsoft Project have that encourages the user to establish the project calendar and calendar options before entering tasks.

Project provides access to calendars available for use in a project through the “Change Working Time” function. Think of Change Working Time as an access point to the group of calendars that will be available to be used in your project. You can use any calendar as the project, task, or resource calendars. When you adjust a calendar through Change Working Time, you’re not assigning any specific calendar as the project calendar.

To assign a project calendar, for all versions of Microsoft Project click on:

Project | Project Information

Calendar option settings should be specified before entering tasks. If the settings are changed after tasks are entered, the duration values most likely will be affected. These settings are specified for each project. However, in Project 2010 you can set them to be consistent for all new projects.

To view and change the Calendar options for all projects in Project 2010, click on:

File | Options | Schedule

If you’re using an earlier version of Project and you want to view and change calendar options, click on:

Tools | Options | Calendar

The Calendar settings that should be addressed for projects are default start and finish times as well as hours per day, hours per week, and days per month.

The values for default start and finish times are needed to establish the start and finish times of tasks if times aren’t specified. In other words, if the tasks contain relationships, times will be calculated based on the relationships. Tasks might also have a constraint that will specify a time. If neither of those situations exists, this is the time that will be used to schedule a task.

When a task is entered, the values in these option fields will be used to determine the number of hours of work that will occur per day, per week, or number of days per month. The values in the options shouldn’t be changed after tasks have been entered. To see the effect of making these changes, here are some examples.

I’ve entered Task 1 into a project file:

Ask the Experts: The Case of the Calendar Changes

I’ve set calendar hours per day to eight:

Ask the Experts: The Case of the Calendar Changes

Here is the result of changing that setting from eight hours to seven:

Ask the Experts: The Case of the Calendar Changes

Note that the Duration changed to 1.14 days. The task picked up the value of one day equaling eight hours when it was entered, and it will hold that value. The setting only affects future tasks that are entered. The existing tasks keep the setting of eight hours as one day on Task 1. The 1.14 days that shows up is the duration that will be necessary to accommodate the eight hours the task requires when a day contains a possible seven hours of work.

Below, in Figure 4, I’ve added Task 2 with the calendar option of hours per day set to seven. Note the difference in the task lengths.

Ask the Experts: The Case of the Calendar Changes

The next step is to assign a resource and then change the calendar to see the result.

In the next example I’ve assigned a resource to both tasks using the default calendar times of eight to five. Note that Task 1 is for eight hours of work and Task 2 is for seven hours of work.

Ask the Experts: The Case of the Calendar Changes

Next I change the Project Calendar to reflect that the work day is four hours long. Here’s the result of the adjustment to the assignments. Note that the work day for each day doesn’t exceed four hours. The duration of the tasks are affected as well.

Ask the Experts: The Case of the Calendar Changes

So best practice says to enter Project Calendar and Calendar option settings before the tasks are entered.

Note! When using the import function to a new project, the values might not be set correctly, particularly in Microsoft Project versions prior to 2010. Consider creating a file, entering the correct settings, and then importing tasks by appending them to the end of an existing project.

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Ask the Experts: The Case of the Calendar Changes

Wayne from Santa Fe, NM asks: I created a project containing 400 tasks. After entering the tasks I realized that my calendar wasn’t correct and made some changes. I also […]

4 min read
•over 14 years ago•Updated 5 months ago•
E
Ellen LehnertAuthor
Project Management
Microsoft Project
Best Practices
Productivity
E
Ellen Lehnert

Content Writer

Ellen Lehnert, PMP, Microsoft Project MVP, MCP, is a independent consultant and trainer on Microsoft Project and Project Server. She has taught Microsoft Project over 400 times and is the author of  MS Project 2010 and 2013 published courseware. Ellen is also a contributor and tech editor for many reference books, a developer for the Microsoft Project certification tests and is a frequent meeting speaker for Microsoft, MPUG and PMI. Contact Ellen at ellen@lehnertcs.com.

View all articles by Ellen Lehnert
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Maintaining the Human Element of Leadership in a Technological World
Articles
1 min read

Maintaining the Human Element of Leadership in a Technological World

Learn how leaders can maintain humanity in technology-driven workplaces through emotional intelligence, role clarity, psychological safety, and meaningful recognition.

A
Anonymous
5 days ago
Read
5 reasons to attend: 4 pillars of Project Online to be Aware of When Migrating
Articles
1 min read

5 reasons to attend: 4 pillars of Project Online to be Aware of When Migrating

Erik van Hurck shares four pillars for a successful Project Online migration, covering scope, data prep, execution, and user adoption from real enterprise experience.

A
Anonymous
13 days ago
Read
It’s Not Unusual: Why Projects Behave Badly and Why Good PMs Expect It
Articles
1 min read

It’s Not Unusual: Why Projects Behave Badly and Why Good PMs Expect It

Projects misbehave because people behave normally — Ronald B. Smith explains why experienced PMs stop being surprised and start building systems that bend without breaking.

A
Anonymous
18 days ago
Read
Explore All Articles