You have probably noticed that some of the most powerful views in Project have an upper part and a lower part. These two part views are called Combination Views. The upper part is called the Primary. It is for identifying a single component such as a resource or a task. The bottom part is called the Details. It is to provide more information about what is selected in the Primary. A great example in every version of Project is the “Task Entry” View shown below.

(Click on Figure to expand)

The “Task Entry” View is comprised of a “Gantt Chart” in the Primary and a “Task Form” in the Details. Select a task in the “Gantt Chart” and the “Task Form” tells you literally everything you need to know about the task including resources assigned and the work assigned to them, task predecessors, task type and whether the task is effort driven or not. If you right click on the “Task Form”, Project will offer you a list of other Details available such as “Work”, “Cost” and “Schedule”.

Another great View to aid in resource leveling is the “Resource Allocation” View. “Resource Usage” View is the Primary and “Leveling Gantt” View is the Detail.

(Click on Figure to expand)

This Combination View is designed to highlight resource overallocations in the Primary and show any concurrent or overlapping task assignments in the Details. It’s a great start to understanding the impact of the schedule to your resource assignments.

When you have solved unacceptable overallocations by using leveling techniques, the “Leveling Gantt” will illustrate the pre leveled and post leveled schedule for your analysis.

You aren’t limited to the “canned” Combination Views. You can create your own!  Some great combinations are the “Resource Graph” over the “Gantt Chart”, “Gantt Chart” over the “Relationship Diagram” and “Resource Sheet” over the “Resource Graph”.

If you’ve never created a Combination View, Project 2013 and 2016 Help has a great tutorial under “Split a view”. Other versions use similar language.

Give Combination Views a try. You’ll save a little time analyzing and problem solving!

Check out the NEW Do’s and Don’ts Bootcamp, which delivers Microsoft Project Management proficiency (and credibility) in just three hours of training!

This article was originally published at https://winprojblog.blogspot.com/2017/03/dos-and-donts-use-combination-view-to.html. Used with permission.

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM GlossaryOur Faculty

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUGMaster Project User Group

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Do’s and Don’ts: Use a Combination View to Ease Problem Solving

You have probably noticed that some of the most powerful views in Project have an upper part and a lower part. These two part views are called Combination Views. The […]

2 min read
•over 8 years ago•Updated 10 months ago•
S
Sam HuffmanAuthor
Project Management
Microsoft Project
Best Practices
Productivity
S
Sam Huffman

Content Writer

Sam Huffman first gained insight into Microsoft Project while working as a member of the MS Project development and support team. He has maintained his depth of knowledge of MS Project with each release and is a leading authority in the use and features of MS Project, Project Server and Project Online. Since the early 1990's Sam has honed his instruction skills by delivering training programs to thousands every year. Sam is a frequent content contributor to the Microsoft Project User Group (MPUG) and speaks to groups often about MS Project, Enterprise Project Management and the discipline of Project Management. He was awarded Microsoft Most Valuable Professional from 2010-2017. Check out his blog on MS Project. The softcover version of my newest book Microsoft® Project Do’s and Don’ts is now available for purchase! It is portable, brief and to the point so you can find help when you need it. Through tips, best practices and examples it will help you jumpstart your project!

View all articles by Sam Huffman
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Collaboration challenges in remote projects (and how to fix each one)
Articles
1 min read

Collaboration challenges in remote projects (and how to fix each one)

Discover 5 common remote project collaboration challenges, from knowledge silos to unclear ownership, and learn practical ways to keep teams aligned and work moving.

A
Anonymous
3 days ago
Read
An Introduction to the PMI Practice Standard for Scheduling Conformance Index
Articles
1 min read

An Introduction to the PMI Practice Standard for Scheduling Conformance Index

Learn how the Conformance Index in PMI’s Practice Standard for Scheduling scores a CPM schedule model, and how to assess its components in any scheduling tool.

A
Anonymous
15 days ago
Read
A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need
Articles
1 min read

A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need

Part II of the PM Halloween survival guide takes on shape-shifting requirements and dependencies that won’t stay resolved, with practical defenses for each.

A
Anonymous
about 1 month ago
Read
Explore All Articles