Shelley asks: I am working with a resource pool that has about 30 sharer files. How can I work with resources from the pool along with some resources that are only working on one project?

I have set the workgroups for the “local” resources as “none” (as you would if you were using Microsoft Project Server), but the pool still picks them up. I don’t want this to happen because some of customized fields in the resource pool are restricted, and the pool sends a message that it can’t copy a value to a restricted field, even a blank.

So I need to figure out how I can stop the pool from picking up these new resources.

Answer: In order to create a shared resource pool, create a Project called “Master Project” and within the Resource Sheet create all your Project Resources that you like to manage.

Figure 1: A sample Master Project.

Ask the Experts: How Resource Sharing Works in a Master Project

Now create the Project files for each project you wish to manage using the Resource Pool from Master Project. Create the new project (in my example, it’s Project 1), then select Tools | Resource Sharing | Share Resources.

Figure 2: Specifying the Resource Pool from which to pull resources.

Ask the Experts: How Resource Sharing Works in a Master Project

Ensure that you use the resources in your Master Project. Select OK and all resources held in the Master Project will also be displayed in your schedule.

Figure 3: Resources held in Master Project will display in your project.

Ask the Experts: How Resource Sharing Works in a Master Project

You can now use these resources for your own project, and the Master project will be able to see the allocation of the resources on your project.

Shelley responds: The description Marc supplied is exactly how I set up my pool. Because I have about 30 sharer files and I also needed to create a master plan that contained all 30 sharers, I called my file “Resource Pool” and linked each sharer to that before inserting it into my master file.

So, knowing there isn’t a way to set it up with local and global resources is a great help, and I’ll go ahead and remove the restrictions I placed on some of the customized fields I put in the pool so it easily picks these new resources up. A note to other readers: Don’t set up any restrictions on customized fields to prevent users being told over and over that certain fields can’t be copied to the pool. That becomes very frustrating for the user. Plus when those little annoying things happen, it’s harder to get buy-in for using a pool.

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM GlossaryOur Faculty

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUGMaster Project User Group

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Ask the Experts: How Resource Sharing Works in a Master Project

Shelley asks: I am working with a resource pool that has about 30 sharer files. How can I work with resources from the pool along with some resources that are […]

2 min read
•over 17 years ago•Updated 10 months ago•
M
Marc SoesterAuthor
Project Management
Microsoft Project
Best Practices
Productivity
M
Marc Soester

Content Writer

Marc Soester is the Managing Director of i-PMO, an organisation dedicated to successfully implement Microsoft's Enterprise Project Management (EPM) solution throughout Australia. Marc and his team have extensive expertise in the implementation of Microsoft Project Server and Portfolio Server as well as conducting training in Project. He has more then six years of experience implementing EPM solutions and is Australia's first and currently only Project MVP (Most Valuable Professional). You can contact him at marc.soester@i-pmo.com.au.

View all articles by Marc Soester
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Collaboration challenges in remote projects (and how to fix each one)
Articles
1 min read

Collaboration challenges in remote projects (and how to fix each one)

Discover 5 common remote project collaboration challenges, from knowledge silos to unclear ownership, and learn practical ways to keep teams aligned and work moving.

A
Anonymous
1 day ago
Read
An Introduction to the PMI Practice Standard for Scheduling Conformance Index
Articles
1 min read

An Introduction to the PMI Practice Standard for Scheduling Conformance Index

Learn how the Conformance Index in PMI’s Practice Standard for Scheduling scores a CPM schedule model, and how to assess its components in any scheduling tool.

A
Anonymous
13 days ago
Read
A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need
Articles
1 min read

A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need

Part II of the PM Halloween survival guide takes on shape-shifting requirements and dependencies that won’t stay resolved, with practical defenses for each.

A
Anonymous
about 1 month ago
Read
Explore All Articles