Back to ArticlesBack

Join 50,000+ PM Professionals

Get expert PM insights, PMP prep tips, and earn PDUs with exclusive content delivered weekly.

Protected by reCAPTCHA: Privacy & Terms

MPUG - Master Project User GroupMPUG

Nancy asks, “I have been a project controller for about seven years. I have a problem that I cant figure out. My % Complete column has stopped calculating. Also, the Actual Duration and Remaining Duration are not being updated either. Actual Duration is always zero even though its well into the task. So Remaining Duration equals Duration. What would cause that?”

Answer: This one is really puzzling. After reviewing the MPP file sent, I wasn’t able to see why the % completed doesn’t calculate. I have checked the settings which, are all fine. Then I exported the project into an XML file and re-imported it ( just in case the schedule is corrupt); but this didn’t change the behavior (which is a bummer).

I’ve also noticed that some % completed updates actually work. Task 31, for example, works fine, but Task 3 doesn’t work at all in regards to the % complete. It seems that a combination of settings and corruption could create this effect. So here’s how I suggest you make it work. (I assume this isn’t a Project Server environment, but only an MPP file.)

1. Save the project as an XML file.
2. Open the XML file in Microsoft Project and create a new project.
3. Go to tools | option. Within the Calculate Tab select “Updating Task Status updates Resource Status.”
4. Save the project.

Nancy replies: “Well, thank goodness! It’s in a Project Server environment, so I skipped steps 1 and 2. It still worked. Thank you so much!”

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM GlossaryOur Faculty

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUGMaster Project User Group

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Ask the Experts: When % Complete Won’t Calculate

Nancy asks, “I have been a project controller for about seven years. I have a problem that I cant figure out. My % Complete column has stopped calculating. Also, the […]

2 min read
•over 17 years ago•Updated 10 months ago•
M
Marc SoesterAuthor
Project Management
Microsoft Project
Best Practices
Productivity
M
Marc Soester

Content Writer

Marc Soester is the Managing Director of i-PMO, an organisation dedicated to successfully implement Microsoft's Enterprise Project Management (EPM) solution throughout Australia. Marc and his team have extensive expertise in the implementation of Microsoft Project Server and Portfolio Server as well as conducting training in Project. He has more then six years of experience implementing EPM solutions and is Australia's first and currently only Project MVP (Most Valuable Professional). You can contact him at marc.soester@i-pmo.com.au.

View all articles by Marc Soester
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

An Introduction to the PMI Practice Standard for Scheduling Conformance Index
Articles
1 min read

An Introduction to the PMI Practice Standard for Scheduling Conformance Index

Learn how the Conformance Index in PMI’s Practice Standard for Scheduling scores a CPM schedule model, and how to assess its components in any scheduling tool.

A
Anonymous
8 days ago
Read
A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need
Articles
1 min read

A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need

Part II of the PM Halloween survival guide takes on shape-shifting requirements and dependencies that won’t stay resolved, with practical defenses for each.

A
Anonymous
27 days ago
Read
Context Engineering for Project Managers: Give AI the Project, Not Just the Question
Articles
1 min read

Context Engineering for Project Managers: Give AI the Project, Not Just the Question

Learn how to choose, date, and source the project information you give AI, so its risk analyses, status reports, and change request reviews reflect your actual project.

A
Anonymous
about 1 month ago
Read
Explore All Articles