Sai Prasad

Forum Replies Created

Viewing 15 posts - 91 through 105 (of 145 total)
  • Author
    Posts
  • in reply to: Budget as Resource #384626
    Sai Prasad
    Participant

    VeeJo – I agree with Larry that resource plan should help you to share resources across project files. To address the second part of your question about budget cost to be tracked and assigned to the respective project, you can create these budget costs resources as budget resources in the resource pool file. Refer to Budget Cost (task field) in this article https://support.office.com/en-us/article/Budget-Cost-fields-debac6b2-48fb-4314-b1a5-8a5f0979f6cb

    Sai Prasad
    Participant

    Hi,

    I am tested the below approach in Project 2010 and hope it applies to Project 2013 too
    1. Exported task details that includes Unique Id and % Complete to Excel workbook
    2. Updated the % complete in Excel workbook
    3. Made sure default task mode is Auto Schedule, otherwise during merge Project is unable to calculate and update Actual Start, Actual Finish and other tracking fields
    4. Import the Excel workbook using Merge option.
    5. Since you have exported and importing the same file, the field mapping will be preset
    6. Complete the wizard, and you should see % complete updated in Project file

    Regards
    Sai

    in reply to: MS-Project Book Technical Review: Any volunteers? #382286
    Sai Prasad
    Participant

    Ulhaas – I will be glad to review the book. Please see my profile https://www.linkedin.com/in/bsaiprasad

    in reply to: MS Project 2013 Critical Task Text Formatting #367516
    Sai Prasad
    Participant

    Mike – I am not able to reproduce the issue. I followed the same steps in Project Professional 2013 – changed the text style of critical tasks, marked a critical task completed, the color changed to black (the default color). Do you mean to say for some tasks the color changes and for some tasks it works correctly? Also, try clearing the formatting that might have been set on some these tasks by first selecting all the tasks, then click Task ribbon, in the Editing group click Clear .. Clear Formatting. This action will ensure any font color changed on that tasks will be cleared and the text style font color will be applied.

    in reply to: Progress lines in MS Project 2010 #365393
    Sai Prasad
    Participant

    I agree with Larry. You can’t do it with Progress lines. The work around is hide the summary tasks in the Gantt Chart. You can create a filter (View tab > Filter drop down … New Filter) and copy the filter definition of Summary. In the Filter definition dialog, change the condition to “Summary equals No” and clear Show related summary tasks. Apply this new filter. It will display all tasks except summary tasks. Now apply the progress line on this view.

    Sai Prasad
    Participant

    Thanks for this initiative to promote Microsoft Project

    in reply to: Micorsoft Project 2013 EditCopy/Paste command #349037
    Sai Prasad
    Participant

    Keshava Moorthy – I have limited knowledge about 2003, but I agree with you in Project 2010 and 2013 copy the summary task just copies on its name. So, the option is you need to iterate the complete task list and do the copy

    Sai Prasad
    Participant

    Chantal – Project uses Gregorian Calendar to define the months of the year and this cannot be changed.

    in reply to: how can I calculate duration of a summary task? #300882
    Sai Prasad
    Participant

    You are welcome

    in reply to: how can I calculate duration of a summary task? #300879
    Sai Prasad
    Participant

    Gianluca Coppola – Thank you. Have you selected “Use formula” for “Calculation for task and summary rows” — see the picture in my previous reply?

    Sai Prasad
    Participant

    Great question. First, let me answer your first question on the locations Project searches for Global.MPT
    1. The current folder
    2. The user’s profile folder
    3. The user’s profile language folder
    4. The folder where the Winproj.exe file is located
    5. The Winproj.exe language folder
    Source: More information section from https://support.microsoft.com/kb/163093

    On your second question on sharing Global.MPT use the following steps
    1. Copy Global.MPT to shared folder (like \\myshare\project)
    2. Ask each user, to create a short-cut of Project on their desktop
    3. Edit the short cut and set the Start In folder to be shared folder
    4. Now, the user launches Project using this short cut, Project checks the Start In folder rather than current folder.

    Sai Prasad
    Participant

    This is very odd. What is the version number do you see in File > Account … About Project

    Project Professional – Project1

    in reply to: how can I calculate duration of a summary task? #300854
    Sai Prasad
    Participant

    Gianluca Coppola – By solar days, I suppose you meant calendar days between start and finish. Insert a Number1 column and you can use DateDiff(). DateDiff(“d”,[Start],[Finish]) returns the number of calendar days between Start and Finish but this function will return a value one less that what is expected. For example, for Start = 1 Jan, Finish = 1 Jan, this function will return 0 but we expect 1. So, in the formula add 1 to the returned value. Let me know if this helps.

    Sai Prasad
    Participant

    Harold – You can ask Project to respect the Start and Finish date by changing the Task Mode to Manually Scheduled. This will ensure as you increase/decrease work the start and finish won’t change. Now change your view to Task Usage (View ribbon). In Time-phased data (right side) enter the 8 hours for the first two days and make edits for the remaining days left.

    in reply to: Allocation of multiple resources to one task #300797
    Sai Prasad
    Participant

    Matt – Since you have hinted one of the resource has no allocation for a period of 5 weeks, check if there are exceptions (holidays) set for this resource. What is the Task type and Effort driven? It would be good if you can provide a screenshot of this assignment?

Viewing 15 posts - 91 through 105 (of 145 total)